Activity Duration

Profile Photo Venkataramiah S Annapragada
23/12/2018 0 View Comments0

Number of work periods needed to complete the activity.
Duration of an activity is calculated using the Task Rule which is as follows :

             Work = Duration * Resource Units

i.Work is the Effort estimated for the activity. Various Estimation techniques discussed previously can be used. This is usually expressed in hours.

ii.Resource Units equals the number of resources that are assigned to the activity and the number of hours per day they are available for this activity.

iii.Duration calculated from above Rule is usually expressed in days.

Example :

An High Level Design Document is required to be prepared. It’s estimated effort is 40 hours. Two resources are assigned to it. Both of them can spare 4 hours each daily for this activity. What is the Duration of this Activity ?

0 Dislike
Follow 1 Loading Spinner
Default Profile Photo

Please Enter a comment

Submit

Other Lessons for You

7 Simple Ways to Make Your Day More Productive
There are only so many hours in a day. Being more productive means getting more out of the limited time we have available. Despite how productive you might already be, odds are you can enhance your productivity...
Profile Photo

MS Project: Linking tasks of other projects
In MS Project, user may want to create a dependancy between tasks of multiple projects, which is also called as external dependancy. This video explains how to create external dependancy in MS Project...
Profile Photo

MS Project: Manual and Auto schedule tasks
Tasks can be scheduled in MS Project in two ways - manual scheduling and automatic scheduling. Manual scheduling gives the users control over how tasks are scheduled and on the other hand auto schedule...
Profile Photo

Learning is Planning and then achieving.
Self-learning is the best learning. Reading the content twice or thrice makes an individual cover about 40% of the chapter and is subject to the grasping power and the prior interest as well. Make...
Profile Photo

MS Project: Manual and Auto schedule tasks
Tasks can be scheduled in MS Project in two ways - manual scheduling and automatic scheduling. Manual scheduling gives the users control over how tasks are scheduled and on the other hand auto schedule...
Profile Photo
X

Looking for PMP Training Classes?

The best tutors for PMP Training Classes are on UrbanPro

  • Select the best Tutor
  • Book & Attend a Free Demo
  • Pay and start Learning

Learn PMP Training with the Best Tutors

The best Tutors for PMP Training Classes are on UrbanPro

This website uses cookies

We use cookies to improve user experience. Choose what cookies you allow us to use. You can read more about our Cookie Policy in our Privacy Policy

Accept All
Decline All

UrbanPro.com is India's largest network of most trusted tutors and institutes. Over 55 lakh students rely on UrbanPro.com, to fulfill their learning requirements across 1,000+ categories. Using UrbanPro.com, parents, and students can compare multiple Tutors and Institutes and choose the one that best suits their requirements. More than 7.5 lakh verified Tutors and Institutes are helping millions of students every day and growing their tutoring business on UrbanPro.com. Whether you are looking for a tutor to learn mathematics, a German language trainer to brush up your German language skills or an institute to upgrade your IT skills, we have got the best selection of Tutors and Training Institutes for you. Read more